Government PoliciesYEIDA Editorial Team (Real Estate Research Analyst)Posted on: Oct 23, 2026Updated on: Oct 24, 2026
50 views
Share:in𝕏

YEIDA Residential Plot Construction Rules: FAR, Setbacks, Map Approval and Fees

YEIDA residential plot construction rules, FAR, setbacks, building map approval and fees

YEIDA building regulations covering residential plot construction, permitted FAR, ground coverage, setbacks and approval procedures.

Planning to build a house on your YEIDA residential plot? Before construction, you need to understand the permitted building area, ground coverage, setbacks, height limits, map approval process and construction deadline.

YEIDA follows its Building Regulations, 2010, along with applicable amendments, scheme conditions and lease terms. The rules determine how much you can build and what you need to do before moving into your house.

What are the construction rules for YEIDA residential plots?

You must obtain building plan approval before starting construction. Your house must follow the approved layout, permitted residential use and applicable building regulations.

The main rules are:

  • Get your building map sanctioned by YEIDA before construction.

  • Follow the approved FAR, ground coverage, height and setbacks.

  • Provide the required parking, drainage, water supply and other services.

  • Do not subdivide your individual residential plot.

  • Complete the required construction and obtain the applicable occupancy certificate.

The regulations applicable to your sector and the date of its allotment matter. Check your allotment letter, lease deed and approved sector layout before finalising your house design.

How much construction is allowed on a YEIDA residential plot?

Two important limits determine how much you can build: ground coverage and FAR.

Ground coverage is the percentage of your plot covered by the building at ground level. FAR, or Floor Area Ratio, is the total floor area counted under FAR divided by the plot area.

The following summary reflects the residential plot categories in YEIDA's published Building Regulations, 2010.

Plot size

Maximum ground coverage

Maximum FAR

Up to 350 sq. m.

75%

1.80

Above 350 to 500 sq. m.

65%

1.80

Above 500 to 750 sq. m.

60%

1.50

Above 750 to 1,500 sq. m.

55%

1.50

Above 1,500 to 2,000 sq. m.

53%

1.50

Above 2,000 to 5,000 sq. m.

50%

1.50

Above 5,000 to 20,000 sq. m.

45%

1.20

Above 20,000 sq. m.

40%

1.00

The table gives the general limits, but the applicable scheme and approved layout must also be checked. Your architect should confirm the exact category and permitted FAR before preparing the drawings.

How much can you build on a 200 sq. m. YEIDA plot?

Suppose you own a 200 sq. m. residential plot.

At 75% ground coverage, the building footprint can cover up to 150 sq. m. At FAR 1.80, the total floor area counted under FAR can reach 360 sq. m. across all floors.

These are theoretical limits. Setbacks, height, parking and other requirements may reduce the area available in your final design.

What are the setback and height rules for YEIDA plots?

A setback is the open space between the building and the plot boundary. It provides space for access, light and ventilation.

YEIDA's residential building table specifies setbacks according to plot size. The front setback increases as plots become larger, while side and rear setbacks must follow the applicable sector layout and the regulations in force when the sector was initially allotted.

For reference, the front setback values shown in the regulations include:

Plot size

Front setback

Up to 150 sq. m.

2.5 metres

Above 150 to 200 sq. m.

2 metres

Above 200 to 300 sq. m.

3 metres

Above 300 to 350 sq. m.

3.25 metres

Above 350 to 400 sq. m.

4 metres

Above 400 to 500 sq. m.

4.5 metres

Above 500 to 1,000 sq. m.

5 metres

These figures must be checked against the applicable sector plan. Do not finalise a drawing using only a general setback table.

The general maximum height for an individual residential plot is 15 metres under the published regulations. However, airport related height restrictions or other site specific requirements may apply. Ask your architect to check whether your plot needs additional height clearance before preparing the plan.

Can you build a basement, stilt parking and multiple floors?

YEIDA permits certain additional features under specific conditions.

Basement: One basement may be allowed for parking, services and storage within the permitted building envelope. Its structure, height and position must meet the applicable requirements.

Stilt parking: Stilt parking up to 2.4 metres from the floor to the bottom of the beam is allowed free from FAR on plots of 112 sq. m. and above.

Balconies: Balconies up to 1.5 metres wide are generally excluded from FAR under the residential rules. Wider balconies may have a portion counted in FAR.

Dwelling units: The regulations allow up to two dwelling units on plots up to 100 sq. m., up to three on plots above 100 sq. m. and up to 500 sq. m., and up to four on plots above 500 sq. m. A servant quarter counts as half a dwelling unit.

How do you get YEIDA building map approval online?

YEIDA processes building plan sanction and completion applications online through its Building Plan Management System (BPMS). The online only process has applied since 1 August 2024.

Follow these steps:

  1. Hire a registered architect. Choose an architect registered with the Council of Architecture and YEIDA. The architect prepares your site plan, floor plans, elevations and service drawings.

  2. Log in to BPMS. Open the official YEIDA Building Plan Management System and log in using your existing PMS, PIMS or CCP credentials, as applicable. Complete the OTP verification.

  3. Select your architect. Choose the architect from the available list and submit the request. The architect must accept the appointment.

  4. Submit the drawings for Pre-Check. The system checks technical drawing details such as colours, layers, geometry and closed polylines. Correct any errors and upload the drawing again.

  5. Complete drawing scrutiny. Once Pre-Check passes, Smart DCR compares the drawing against applicable YEIDA building rules and amendments. Your architect must correct any objections before proceeding.

  6. Pay the fees online. Once the drawing passes scrutiny, pay through the BPMS payment process using the required PIMS credentials. Offline payments are not accepted for this process.

  7. Upload the signed drawing and complete submission. YEIDA does not require a paper hard copy through BPMS, but the duly signed scrutiny approved drawing must be uploaded.

  8. Obtain sanction before construction. Keep your building permit and approved drawings at the construction site. Build according to the sanctioned plan.

Use the official BPMS portal for the latest application instructions, drawing manuals and sample residential plans.

What are the YEIDA building plan approval fees?

The current BPMS FAQ lists the following fee schedule. These charges depend on the application and covered area, so the final amount should be checked using the portal's fee calculation.

S.No

Building Permit Fees

Rate (in INR)

Applicability

1.

For all type of buildings, covered for all floors

15.00 per sq. mtr.

Covered Area

2.

Layout Plan – Area upto 4.0 hectare

1.00 per sq. mtr.

Plot Area

3.

Layout Plan – Balance Area

0.50 per sq. mtr.

Plot Area

4.

Malba Charges for plots upto 2000 sq mtr.

10.00 per sq. mtr.

Covered Area

5.

Malba Charges for plots upto 2001 sq mtr. to 10,000 sq mtr.

5.00 per sq. mtr.

Covered Area

6.

Malba Charges for plots above 10,000 sq mtr.

2.00 per sq. mtr.

Covered Area

7.

Revision Fees - a. Layout Plan

0.50 per sq. mtr.

Plot Area

8.

Revision Fees - b. Building Plan

25% of processing fee

Covered Area

9.

Revalidation Fees - (for 5 years) if applied within validity

10% of processing fees

10.

Revalidation Fees - (for 5 years) if applied outside validity

Original Permit Fees

11.

Temporary Structure - a. Labour Hutment

0.25 per sq. mtr.

Covered Area

12.

Temporary Structure - b. Other Uses of Temporary Structures

25% of the processing fees

Covered Area

13.

Completion Fees

10.00 per sq. mtr.

Covered Area

14.

Layout Fees ( Plot Area upto 4 hectare)

0.50 per sq. mtr.

Plot Area

15.

Layout Fees ( Balance Plot Area above 4 hectare)

0.25 per sq. mtr.

Plot Area

The BPMS FAQ also lists a ₹500 site visit fee for each subsequent visit if the authority has issued two objection letters and the required corrections remain incomplete.

Separate charges apply to layout plan applications and other types of work. Use the fee calculator on the BPMS portal to confirm the amount for your particular application.

What is the minimum construction required on a YEIDA plot?

The residential regulations specify a minimum covered area for sanction and completion of 40 sq. m. or 50% of the maximum permissible ground coverage, whichever is higher, subject to the applicable lease conditions.

For the occupancy certificate, the house must include the required basic facilities and building work, including:

  • Finished flooring and electrical wiring.

  • Plumbing and fittings in at least one toilet and kitchen.

  • The required trees and landscaping.

  • A number plate, boundary wall and gate.

  • External doors and windows that make the house lockable.

  • Rainwater harvesting and other required services, where applicable.

The final inspection also checks compliance with the sanctioned plan. Unapproved construction or violations must be corrected before the authority can grant the required approval.

How long do you have to complete construction?

Your construction deadline depends on your scheme, lease deed and applicable authority orders. Do not assume that every YEIDA plot has the same deadline or extension charges.

For the RPS10/2026 residential scheme, published scheme guidance specifies completion within three years of lease deed execution and obtaining the occupancy certificate within that period. Check the exact conditions stated in your own allotment and lease documents.

YEIDA has also announced a free extension until 31 December 2026 for eligible existing residential plot allottees who completed their lease deeds but could not start construction because of land disputes and related delays. This relief does not automatically apply to every plot. Contact YEIDA to confirm eligibility and any conditions attached to the extension.

?

Frequently Asked Questions (FAQs)

For plots up to 500 sq. m., the published general FAR is 1.80. Larger plot categories have different limits.